125th Anniversary of the
Opening of the
Prince of Wales Bridge The Prince of Wales Bridge, the first railway bridge linking Ottawa and Hull, was opened to regular traffic 125 years ago on 17 January 1881. In this article we will look at its construction and then explore a few of the changes and significant events that have subsequently taken place. [1] Background.
The railway between Montreal and Hull was opened by the Quebec, Montreal, Ottawa and Occidental Railway (Q.M.O. & O.) on 27 December 1877 and was extended to Aylmer on 6 August 1879. [2] The Q.M.O. & O. provided the most direct route between Ottawa/Hull and Montreal because the only other option at that time was the St. Lawrence and Ottawa Railway to Prescott and a transfer to the Grand Trunk Railway. Many travellers on the Q.M.O. & O. were faced with a difficult journey between Ottawa and Hull over rough roads and were frequently at the mercy of the (horse drawn) cab drivers and others who made the arrival and departure of trains at Hull a raucous event. Passengers were very frequently amused, on the arrival of the train at Hull, by the conductor opening the first class door and calling out “Ottawa”, then going to the second class car and calling out “Hull”. The Q.M.O. & O., which was a department of the Quebec government, planned to extend its line across the Ottawa River into the Chaudiere district of Ottawa, now known as Lebreton Flats. Surveys of possible sites for the Chaudiere railway bridge were carried out as early as 1873 when a location using Amelia Island in the Chaudiere was investigated. Later surveys used Lemieux Island, the route finally chosen. The successful bidder for the construction of the earthworks and piers, Horace Jansen Beemer, was announced on 28 April 1879. Mr. Beemer’s bid of $112,873.10 was the lowest of 39, the highest being $223,530.50. This was Beemer’s first construction work in the Ottawa/Hull area. [3] Earthwork and
Construction of the Piers.
This
plan is dated 27 March 1879 and shows the location of the bridge and
the
approach from Hull at the top (north) to Ottawa (Chaudiere) at the
bottom. The connection to the Canada
Central Railway
is shown at point B at the bottom as are the existing
passenger and
freight stations at the Chaudiere. At
the north end, the line left the Q.M.O. & O. Aylmer branch at point
A
just south of the Hull station. The
bridge is, in effect, two bridges with seven spans across the north
channel to
Lemieux Island and a further six spans to Duck Island on the Ontario
shore. From Duck Island considerable
filling was necessary to bring the line to the Canada Central Railway
on the
Chaudiere. The water was not very deep,
the deepest being about 30 feet, however, at times the water flow was
fast and
this was to cause some problems. The
piers were numbered north to south from 1 to 11. (Adapted from National
Archives, NMC 145183)
Mr. Beemer wasted no time and by the third
week of May,
1879, some 30 men were working on the Ontario side of the river. However, labour difficulties soon became
apparent when the workmen went on strike on 3 June.
The reason was wages – the men were paid 85
cents a day and they wanted $1.10. This
did not last very long as on 23 June it was reported that the strikers
were
sitting around on lumber piles watching other men filling their places. As if this weren’t enough, some 35 stone
masons went on strike in early July. Wages,
again, were the problem, the original rates of pay
would only
allow the men to make about 60 cents a day. [4] Work on the piers was assisted by a steam tug which was built in the Hull shipyard of Messrs. J.W. McRae & Co. It was drawn through the city by three spans of horses and launched on the Ottawa River above Ottawa on 4 July, 1879. The boat, with a draught of about 40 inches, was used to haul barges of stone and other materials to the eleven sites for the piers. [5] This
shows a siding being constructed into Bells gravel pit at Britannia on
the
Canada Central line to Carleton Place.
It is constructed to the broad provincial gauge of 5 feet 6 inches and
was used to provide fill for the earthworks on the Ontario side of the
bridge. A steam shovel was used in the
pit. The
new line through Duck Island to the bridge proper passed
over some low ground behind the Canada Central three stall round house
near the
Ottawa River. This required extensive
filling and in July, Mr. Beemer leased two locomotives and 30 cars from
the
Canada Central Railway to haul gravel from Bells Pit at Britannia. [6]
It had been optimistically hoped that the bridge
could be
finished by the end of 1879. However,
trains were still bringing fill in mid October at the rate of 300 cars,
each
containing 11 yards, daily and much filling was also required on
Lemieux Island
after the bridge spans had been put in place. It
was evident that the project could not be completed in
1879 and work
was shut down for the winter, with the exception of a few men in the
Hull quarry
breaking stone for cement purposes. However,
good progress had been made. By the end
of 1879 all four abutments had been completed, with the exception of
the
coping, and nine of the eleven piers had been finished. [7]
It was in December 1879 that the first problem with the rapid flow of water occurred. The Ottawa Citizen of 10 December 1879 explained: “A
barge loaded with clay and having 35 men on board was towed by the
Chaudiere
Bridge tug to pier no. 5 yesterday. The
usual practice is for the tug to go a little above the pier, cast the
barge
loose and let it drop down to the pile, when it is snubbed. This was done yesterday, but the line fell
short of the pier and the barge drifted towards the falls.
The tug immediately backed but was soon
aground and the men in the barge felt anything but comfortable, for
every
moment they were approaching nearer the cataract. A
row boat was manned and put off to their
relief, the rope being carried to the tug by this means just in time to
save
the barge and its crew from going into the Big Kettle.” Mr. Beemer resumed work in mid February 1880 with rip-rapping the southern embankment and protecting the piers from water action. The steam tug was launched on 12 April. [8] Almost immediately there were problems with high water.
From The Canadian Illustrated News of 17 April 1880: “Work
on the Chaudiere railway bridge has been recently resumed, and at pier
5 a scow
was anchored. On board was a portable steam-engine and a centrifugal
pump, the
weight of which is about ten tons. Recently a large cake of ice came
dashing
down the river, and coming into collision with the scow, started her
adrift.
The scow, with its load of freight, rapidly drifted down the current
and went
over the falls. The engine was on wheels, and was found canted over,
but not
injured." “Yesterday
afternoon at three o'clock, another barge used at the Chaudiere bridge
works
went over the falls. This time four men
had a very narrow escape from going over with it. The
barge was loaded with clay used for
puddling at the cofferdam. The tug boat
had cast it loose when near pier No. 6, as was usual, it then having to
be
pushed up to the pier by men on board with long poles.
The current, on account of the high water,
was swifter than reckoned upon, and the barge became unmanageable, and
was
carried down towards the falls. The men
on board were Joseph Dupont, Francis Furlough, Geo. Lapierre and J.
Tooney. The first three named jumped into
the skiff
that was by the side of the barge, and made for one of the wooden piers
used
for holding the booms, in order to fasten a rope to bring the barge to. The man left on the barge threw a rope to
them but it curled round the leg of Dupont dragging him into the water. With great difficulty he swam to an
island. The man left on board was now in
extreme peril. William Connelly, seeing
the danger of the man, immediately went to the rescue in a light boat
and got
up to the barge just as it was entering the rough water of the falls. The man jumped in and it was with extreme
difficulty and only by great exertion that they overcame the strength
of the
current and landed in safety. Connelly
saved the man at the risk of his own life. The
wonder was that it was possible for him to return
after entering the
troubled water. The barge went over the
falls and was captured at Gilmour's booms, below Messrs. McRae and
Co.'s
shipyard.” “The
general manager of the works gave the following account of the
accident:- Yesterday, in company with Mr. Beemer, I made a trip across the river and we found the river so high and the current so strong that orders were given to the river foreman to tie up the tug and make no more trips across the river. This morning, he, (the river foreman, Dennis O'Brien) found he required a few sticks of timber and made one trip to bring them over, taking every necessary precaution, intending, as soon as he returned to lay up the tug until the water went down to the proper height for work again. In coming back they fastened the scow to the boom, in order to let the tug drop down below. The scow was on the inside of Eddy's boom. In dropping down, the scow swung end for end in the eddy and passed over the boom, leaving inside the boom and powerless to render any assistance. The two men on the scow had a lifeboat with them, one of them, Joseph Malboeuf, jumped on the boom and the one that was lost, La Berthiaume, got into the lifeboat, which was immediately swamped after being thrown out of the boat. He swam for the boom and when within a few feet of the boom, for some reason unknown to us turned and swam towards the scow, which was floating down the river about twenty five feet from him. He succeeded in catching a short end of rope hanging from the scow but apparently did not have strength to raise himself. The man in company with him said he would have had no difficulty in reaching the boom, where he would have been safe, if he had not turned to the scow. These are the facts as near as I can gather them from eye witnesses. We shall not float any craft until the water falls.” Work did not resume until mid July, 1880. It proceeded relatively smoothly, apart from the boom of a derrick snapping while loading stones on to a barge on 22 July. A man who was directly under the boom, heard the cracking of the timber and made a dive into the water. He came up, his hat still on his head, and swam to shore and coolly went about his work again. The last stone was laid at a ceremony on 11 October which was accompanied by toasts and some speeches. Mr. Beemer could then concentrate on filling in on Lemieux Island, the first construction train being run over to the island from the south on 16 October. Beemer’s part of the work was finished by the end of November. [11] Gauge of the Ontario Construction Trains The gauge of the construction trains used on the Ontario side is a question which provides many problems for railway historians because, although we have a great deal of information, we don’t have a definitive answer. Mr. Beemer hired two construction locomotives and 30 cars from the Canada Central Railway in July 1879 to bring fill material from Bell’s pit on the C.C.R. main line just west of Britannia. At that time the C.C.R. was broad gauge and the work in 1879 was carried out using broad gauge equipment. After a short break, work was resumed in February 1880 placing rip rap on the southern approach to the bridge. This work had not been completed by the time the C.C.R. changed its gauge to standard in April 1880. [11] With the change of gauge Mr. Beemer was faced with a number of options: 1. Change the gauge of the construction trackage to standard and either: - convert the broad gauge equipment he was already using to standard gauge. This would likely not have been economic bearing in mind that construction equipment is normally very old and approaching life expiry; or - dispense with the broad gauge equipment and complete the rip rap work with different standard gauge equipment. 2. Stockpile all the material needed to complete the rip rap work at the Chaudiere before the gauge of the C.C.R. main line is changed and complete this work using broad gauge track and equipment. This implies expensive double handling. 3. Lay a third rail between Ottawa, Chaudiere, and Bell’s pit and complete the work on the southern approach with the broad gauge equipment already on hand. A further point to be considered is that the C.C.R. was building its main line west of Mackey’s (or Mackie’s), beyond Pembroke, using broad gauge equipment even after the rest of its system had been changed to standard gauge. Two broad gauge locomotives were sent up the line to continue the construction: Last week a
broad gauge
engine was taken up to Mackey's station on board the morning train from
Pembroke. It is to be used for
construction and other purposes above where the track is now laid to,
as the
track above Mackey's is, for the present, to be constructed to the
broad
gauge. Five or six broad gauge cars, to
be used with the engine, went up on board the train here Saturday
morning.
(Ottawa Free Press, 17 May 1880) On 14 June 1880, the Pembroke Observer, said: Tuesday morning last another broad gauge engine and some eight or ten cars of rails went up.( Ottawa Free Press 14 June 1880 (quoting the Pembroke Observer))Is it possible that the two broad gauge engines mentioned were those used by Beemer? Is it possible that the rails had been lifted from a short lived dual gauge section of track between the Chaudiere and Bell’s pit? Canada Central Railway 4-4-0’s Nos. 26, 27 and 28 (built by Taunton in 1870) were still broad gauge when the CCR was acquired by Canadian Pacific in June 1881. [12] One of these was isolated at Renfrew when the gauge was changed in April 1880 and was moved up for the construction work above Mackey’s. The other two are accounted for above so it is just possible that the two locomotives used by Mr. Beemer were from 26, 27 or 28. Work on the bridge superstructure began in August 1880. The materials were delivered in standard gauge cars from the United States so there had to be standard gauge access to the bridge by August 1880. The bridge across the southern channel, on the Ontario side, was completed by October 1880 and it was only then that Mr. Beemer could commence the significant amount of fill work on Lemieux Island. Once again, the question of gauge arises. If broad gauge had been used it would have been necessary to lay a third rail over the bridge as far as Lemieux Island. It is possible
that construction
work on the southern approach to the Prince of Wales Bridge was
completed using
broad gauge equipment after the C.C.R. had converted to standard gauge. It is likely that the fill work on Lemieux
Island was carried out with standard gauge equipment.
However, although we have a lot of
information on the subject there is no firm evidence and all we can
realistically say is that we don’t know.
An aerial view of the bridge looking
from the north, Quebec, side.Lemieux Island is in the centre of the
frame and the newly constructed Ottawa River parkway can be seen in the
background,. City of Ottawa Archives.
Construction
of
the Superstructure The $200,000 contract for the superstructure
was awarded to
Clark, Reeves & Co. of Phoenixville, Philadelphia who constructed
all of
the bridges on the Q.M.O. & O. It
was originally intended that the materials should all be supplied from
the
Quebec side via Montreal. The reason for
this was that the Canada Central Railway was broad gauge and
transshipment
would have been required from standard gauge cars to broad gauge at
either
Morristown or Brockville. However, the
Canada Central converted to standard gauge in April 1880 with the
result that
the materials for the spans on the Ontario side were delivered to
Ottawa via Brockville
while those on the Quebec side came to Hull via Montreal. [13] Prince of Wales Bridge This is a Whipple truss,
developed by Squire Whipple, a stronger version of the Pratt truss.
Patented in
1847, it was also known as the "Double-intersection Pratt" because
the diagonal tension members cross two panels, while those on the Pratt
cross
one. The Whipple truss was most commonly used in the trapezoidal form
--
straight top and bottom chords -- although bowstring Whipple trusses
were also
built. The Whipple truss gained immediate popularity with the railways
as it
was stronger and more rigid than the Pratt. The bridge consists of four abutments and
thirteen
spans. Bridge No. 119.1 (Lachute subdivision mileage) runs from the
Quebec shore to Lemieux
Island. From north to south the seven
spans are: 163’
9”
258’ 7” 138’ 8” 153’ 9” 153’ 7” 153’ 7” 153’ 8” 1204’ Overall Bridge No. 119.5 runs from Lemieux Island to the Ontario
shore. 6 spans of 153’ 9” each 943’ 6” Overall The iron for the spans on the Ontario side
started arriving
on the Canada Central Railway in mid-August 1880.
Work started straight away and on 16 October
construction trains started to run to Lemieux Island.
This created a new recreation for Ottawa
residents who took advantage, during the weekends, to stroll over as
far as the
island to view progress. This must have been a somewhat perilous stroll
because
the wooden guard rails were not erected (by William Mason & Sons,
who cut
the lumber at their mill near the bridge) until
December. Work
did not
start on the Hull side until early October but this proceeded well so
that by
18 November, only one more carload of iron was required for completion.
The
only delay to this part of the work resulted from a storm on 6 November
when
the traveller used in erecting the superstructure, together with some
tools,
blew into the water and was lost. This
delayed completion by about a week. [14] The erection of the superstructure was described in some detail in the Ottawa Free Press of 31 August, 1880: “Putting a bridge
together “First a wooden trestle is
erected between the piers,
starting from a shore end. This trestle
is called false work, as it is only intended to serve a purpose, and
that
purpose is to aid in the erection of the substantial structure that is
to stand
the test of traffic, travel and time. Upon
this trestle work, which is wider than the intended
bridge, a rail
track is laid, and the iron to form the superstructure is distributed. The centre panel is first raised, then the
others along to first one end of the span and then the other, what is
called
"a traveller" being used. When
the iron forming the span is all connected, the trestle work is knocked
out,
and that portion of the bridge sustains itself and a great deal more
when put
to the test. The end columns and top
chords are the principal pieces of iron forming an iron truss bridge of
recent
invention, and after these comes the large floor beams, with four sets
of
longitudinal track stringers for the rails. The
main iron columns and cords are braced together by
diagonal tie bars
and transverse bracing. Each span has a
set of arched brackets with urns on the top corners.
The truss is one of Clark, Reeves & Co.'s
own patent pin connection. The bridge
material is of wrought iron, with the exception of the compressive
strains,
(connecting) which are of cast iron” Employees of Clark, Reeves & Co. started leaving Ottawa on 8 December, 1880, although a number stayed on until 11 January, 1881 to finish up the work. [15] Opening to Traffic
A test was made on the Quebec side on Saturday 4 December, 1880: On Thursday 9 December, 1880 the Ottawa Free Press reported: “It
is expected that trains will be run across the Chaudiere Railway bridge
on
Monday. Mr. Shanly is to act as
government inspector at the testing of the bridge.
In this connection it is understood that
changes will be made in the superstructure of all the bridges on the
Occidental
Railway, in the adoption of a clamp instead of bolt and nuts as a
fastener of
supports, an improvement invented by Clarke, Reeves & Co.” The actual test took place on Monday, 13 December, 1880: “The
bridge was tested yesterday afternoon. Messrs.
P.A. Peterson, Engineer-in Chief; Mr. C.A. Scott,
Assistant
Superintendent; Mr. Davis, Mechanical Superintendent; Messrs. Massey
and
Howard, Assistant Engineers and Mr. Reeves of the firm of Clarke,
Reeves and
Co., of Philadelphia, the contractors for the iron work being present. The test was more than satisfactory and more
than fulfilled the requirements of the specifications.
On the deflexion being taken the first 150
feet spans gave a minimum deflexion of 1/4 inch and a maximum of barely
1/2
inch; the maximum deflexion of the 250 foot span was but one tenth of
an
inch. All the spans, which were in
succession
covered by the five engines brought together as close as they could be,
came up
again and did not show any permanent deflexion. The
bridge is calculated to stand a pressure six times
greater than
ordinarily to be put on it.” [17] Although there was talk in the press of a
formal opening by
the Governor General and invitation cards were sent out I can find no
record of
such an occasion. Possibly, this was
because the new station facilities in Ottawa were not opened until
several
months later and also because of the action of the Dominion government
in
seizing the bridge. [19] Seizure of the
Bridge
Before
the bridge was even open to traffic it
was seized, in mid-November 1880, by customs authorities on the grounds
of
under valuation of material in entry. The Quebec Government money was
garnisheed by the Dominion Government until the matter could be settled. Clark, Reeves & Co. had entered the iron
superstructure at $3.53 per hundred weight, paying $21,780 in duty,
being 25
per cent on $87,130.40. The Customs
Appraiser, who made this seizure on behalf of the Government, held that
duty
should be paid on the material at a value of $4.50 per hundred. The firm objected to this and the matter was
referred to arbitration, Messrs. Taylor ( The report of the arbitrators was placed in the hands of the Minister of Customs on 19 February 1881, and on 7 March it was announced that Clarke, Reeves & Co. would be required to pay a forfeit of $26,000, in addition to the duty already paid. [21] Seizure of the bridge did not affect train services across it. Facilities
at
Ottawa Although Q.M.O. & O. trains started
running regularly
into the Canada Central station in January 1881, this was only a
temporary
expedient until new passenger and freight facilities could be completed. The Quebec government agreed to buy land,
construct and ballast the tracks and pay half the cost of a new
passenger
station at a total cost of $36,800. [22] In
addition, both railways constructed new
freight sheds. The new passenger station
was a little to the east of the original Canada Central one and had its
entrance on Broad Street. The track work
and the station were completed by Horace Beemer. The
new Canada Central freight shed was
opened in early March, 1881and trains were able to enter the new
passenger
station for the first time on 9 May 1881. With the changes taking
place, there
were bound to be minor problems such as derailments caused by
unfamiliarity
with the trackage and the changes being made. [23] What’s in a Name?
I
have been unable to trace
when exactly the bridge was named. This
appears to have been carried out between 1899 and 1915. [15]
It was likely named after the then Prince of
Wales, who later became King Edward the Eighth. The
Prince of Wales’ feathers, which were erected on both
ends of the
bridge, were re-erected on the rebuilt bridge in 1926.
Subsequent
Events
Horace Jansen Beemer, who carried out the earthwork and built the piers, went on to a number of railway contracts in the area. He was responsible for much of the construction of the Pontiac and Pacific Junction and the Gatineau Valley Railways and became president of both. His experience on the Prince of Wales Bridge was put to good use in the construction of the Clarke, Reeves & Co. of
Phoenixville, Pennsylvania went on to build a
number of other bridges in Canada the most notorious of which were the
Ottawa
and New York bridge across the St. Lawrence at Cornwall which fell in
September, 1898 and the Quebec bridge across the St. Lawrence which
fell in
August 1907; both events taking place while the bridge was under
construction.
The Canadian Pacific Railway
acquired all of the
railways then in operation on the Chaudiere. On
28 June, 1886 the first Pacific Express passed over the
Prince of
Wales Bridge on its way from In 1911, Canadian Pacific carried out
strengthening work
on the stone piers. Concrete was
poured down to the bed rock to protect the piers from the heavy
current.
[27]
Reconstruction of the Bridge By the mid
1920’s the original spans had become too weak for
the heavier locomotives that were being brought into service. On 1 August 1926 the work of removing the old
steel and replacing it with heavier steel was begun. [28] The
tops of the piers were lowered to allow room for the new, heavier,
spans. The work, which was completed in
February 1927 and cost $750,000, was done without interruption to
traffic by
the Dominion Bridge Company of
A view of the southern, Ontario, end
of the bridge taken before the graffiti artists took over.
Canada Science and technology Museum Matt-1573. Acquisition by the City of The last
regular passenger train over the bridge was the
North Shore Budd car from
CP Rail RDC-5 9307 (nee CP RDC-2 9100, and
later VIA RDC-1 6147), leased by VIA Rail has just entered the Prince
of
Wales Bridge with Ottawa to Montreal train170 on November 5,
1981. In ten days the train was withdrawn as part of the massive
VIA Rail cutbacks. The sign at the top of the bridge over the
years has been rediced to "INCE OF WALES". Photo by Colin J.
Churcher.
CP C-424 4200, RS-18 u 1812 and RS-18 8792
have just exited the Prince of Wales bridge and are curving through
Ottawa West with a ballast train in June 1983. Photo by Earl
Roberts.
Acknowledgements
I would like to thank the
members of the
Footnotes
[1] Although Hull
is now part
of the City of Gatineau, in this article I shall continue to use the
name
“Hull” by which it was known for most of the life of the bridge.
[2] See my article “First Railway to Aylmer” in Branchline, September 2004. [3] Ottawa Citizen 30 March 1873, 24 January 1878, 28 April 1879; Ottawa Free Press, 28 April 1879. [4] Ottawa Free Press, 20 May , 3 & 4 June, 2 July 1879; Ottawa Citizen, 20 May, 3 & 4 June, 23 June, 3 & 4 July 1879. [5] Ottawa Citizen, 3 and 4 July 1879. [6] Ottawa Citizen and Ottawa Free Press, 14 July 1879; Ottawa Free Press 25 July 1879. [7] Ottawa Free Press, 18 October, 10 December 1879 and 14 January 1880. [8]Ottawa Free Press, 12 February and 4 March, 1880; Ottawa Citizen, 13 February and 12 April 1880. [9]Ottawa Citizen, 13 May 1880. [10] Ottawa Citizen, 1 & 19 June, 12, 19 & 22 July, 12 & 18 October and 4 & 30 November 1880; Ottawa Free Press, 19 June, 12 & 14 October and 2 November, 1880. [11] See my article “The Change of Gauge on the Canada Central Railway” in Branchline, April 2005. [12] Railway and Locomotive Historical Society bulletin No. 83. [13] Ottawa Free Press, 18 and 19 August, 1879. [14] Ottawa Citizen, 21 August, 9 October and 18 November 1880; Ottawa Free Press 20 & 24 August, 24 September, 18 October and 15 December, 1880; Renfrew Mercury, 27 August, 1880. [15] Ottawa Free Press, 7 December 1880; Ottawa Citizen, 8 January 1881. [16] Ottawa Citizen, 7 December, 1880. [17] Ottawa Citizen, 14 December, 1880. [18] Ottawa Free Press 16 and 20 December, 1880, 12 and 13 January, 1881; Ottawa Citizen, 13 and 17 January 1881. [19] Ottawa Citizen, 7 and 10 January, 1881; Ottawa Free Press, January 12, 1881. [20] Ottawa Free Press, 11, 12, 17 and 18 December 1880, 6 and 7, January, 21 February and 7 March, 1881; Ottawa Citizen, 19 and 26 January, 1881; Globe and Mail, 22 February, 1881. [21] Ottawa Free Press, 7 and 16 March, 1881; Globe and Mail, 8 March, 1881. [22] 44 Victoria - Documents de la session (Quebec) 1880. [23] Ottawa Citizen, 30 November, 1880, 4 March, 1881; Ottawa Free Press 14 December 1880, 9 &10 May, 1881. [24] Ottawa Citizen, 20 May, 1881; Ottawa Free Press 21 May, 1881. [25] Commission of Conservation [26] See my article “Centenary of the [27] [28] [29] Transport [30] Information from Ray Farand. Bytown Railway Society, Branchline, January 2006. |
Home Articles